Clubhouse Vegetation Enhancement
Skip to main content
To zoom, hold down Shift and drag a rectangle.
Project Overview
Basics
Clubhouse Vegetation Enhancement
Implementation
The Clubhouse Vegetation Enhancement Project is being implemented on USBR and IID land located along the western shore of the Salton Sea that has become exposed as the Sea has receded in recent years. The project area is 607 acres with construction completed on 399 acres that are on USBR land. The project description has been updated to include expansion of the Clubhouse Vegetation Enhancement onto the adjacent IID parcels.
2021
2021
2027
1/13/2026
Project Attributes
Purpose & Goals
Purpose & Goals
The purpose of this project is to increase the surface roughness through placement of non-erodible organic elements, create swales along contour lines to promote stormwater spreading, and establish and expand native vegetation through stormwater spreading and groundwater supply,
Schedule Status
Design
Complete
Land & Water Rights
Complete
Environmental
Complete
Construction
50% Complete
Notes about Status
The 399-acre Clubhouse Project (USBR) was completed in 2024. The additional acres are expanded areas.
Location
Organizations
Contacts
Katie Burnworth - California Department of Water Resources (DWR) (katie.burnworth@water.ca.gov)
| Contact | |
|---|---|
| Additional Contact |
|
Activities & Outcomes
Expected Activities & Outcomes
| Dust Suppression Acres Counted Towards SWRCB WR 2017-0134 Target | Type: Interim Dust Suppression | 607 acres |
| Jobs Created | 4 | |
| Vegetation Enhancement Performed | Vegetation Type: Halophytic scrub | 607 acres |
Reported Activities & Outcomes
| Dust Suppression Acres Counted Towards SWRCB WR 2017-0134 Target | |||||||
|---|---|---|---|---|---|---|---|
| Type | Total | 2026 | 2025 | 2024 | 2023 | 2022 | Units |
| Interim Dust Suppression | 25 | N/A | N/A | N/A | N/A | 25 | acres |
| Completed Dust Suppression | 399 | 0 | 0 | 31 | 171 | 197 | acres |
| Converted Acres | |||||||
|---|---|---|---|---|---|---|---|
| Converted From | Total | 2026 | 2025 | 2024 | 2023 | 2022 | Units |
| Interim Dust Suppression | 25 | N/A | N/A | N/A | 25 | N/A | acres |
| Jobs Created | |||||||
|---|---|---|---|---|---|---|---|
| Total | 2026 | 2025 | 2024 | 2023 | 2022 | Units | |
| 4 | N/A | N/A | N/A | N/A | 4 | number | |
| Total | 4 | 0 | 0 | 0 | 0 | 4 | number |
| Vegetation Enhancement Performed | |||||||
|---|---|---|---|---|---|---|---|
| Vegetation Type | Total | 2026 | 2025 | 2024 | 2023 | 2022 | Units |
| Halophytic scrub | 399 | N/A | N/A | 31 | 171 | 197 | acres |
| Total | 399 | 0 | 0 | 31 | 171 | 197 | acres |
| No accomplishments to report for: | |
| Year(s): | 2021 |
|---|---|
| Explanation: | Construction began for Clubhouse in late 2021, however no acreage was completed in that year. |
Program Phases
Program Phases
Benefits
Benefits
Endangered Species
Endangered Species
No Endangered Species set for this Project.
Habitat Types
Habitat Types
Project Details
Attachments
Clubhouse Vegetation Enhancement Project Boundary - USBR
- Uploaded On
- 3/27/2025
- File Type
- X-ZIP
- Description
- shapefile of Clubhouse Vegetation Enhancement Project Boundary on USBR property
No attachments
Clubhouse Vegetation and Dust Control (December 2024)
- Uploaded On
- 3/27/2025
- File Type
- Description
- Site map as of December 31, 2024, showing locations of vegetation enhancement and dust control
Clubhouse Vegetation and Dust Control (May 2024)
- Uploaded On
- 7/18/2024
- File Type
- Description
- Site map as of May 21, 2024 shows project progress
Clubhouse Vegetation and Dust Control (June 2023)
- Uploaded On
- 6/27/2023
- File Type
- Description
- Site map as of June 20, 2023 showing locations of vegetation and dust control.
Ficha Informativa en Español
- Uploaded On
- 7/18/2024
- File Type
- Description
Notes
No Notes entered.